b'In the three months following the fire, crews worked alongside the projects engineering team and insurer consultants to assess the damage, clean where they could and develop a remedial plan to restore it to pre-fire conditions. During this time, it was determined that the 15th and 16th floors were beyond repair and required removal, while work on the floors beneath would also require extensive restoration. Undaunted, crews partnered with local restoration specialists Winnipeg Building and Decorating and Di-Tech International to tackle the repairs in a manner that would allow work to progress.As anyone watching our progress over the past few months will note, we started our restoration work at Ledcor Construction Limited. At timeThat is not to say the developmentthe nineth floor and progressed both of writing, the firm is completing thehas completely gone to plan. Ondown and up the tower as floors buildings superstructure with the goalDecember 21, 2019, a fire broke outwere cleaned and restored, adds of sealing it from the elements by on the site that damaged a significantStevens, noting, Logistically, our trade fall 2020. portion of the build. And while therepartners have been exceptional at were no injuries from the blaze, thepivoting their efforts toward the new The interior portion of the projectincident brought considerable damagesequencing, working with suppliers is progressing well, reports Jarrodto the building, including smoke andand manufacturers to re-work delivery Stevens, Senior Project Manager withwater damage throughout. schedules and deliver the required Ledcor. Approximately 30 per centequipment and materials. of the framing and rough-in has beenTo date, the single biggest challengeSince the blaze, crews have nearly completed to date, with the installationhas been the fire, says Stevens.completed the re-installation of the Not only did it halt progress, but it15th and 16th floors and are on track of the buildings electrical, centralforced us to look at the project veryto topping The Arc in August 2020. heating and HVAC systems already differently in terms of schedulewell underway. and sequencing. The entire project teams collective efforts allowed us to make the scheduling and logistic shifts necessary to remain productive and efficient throughout the project, Stevens adds.Youre building REACHING THE TOPFire delays aside, work on The Arc the future. continues to move forward as planned. And though the arrival of COVID-19 has required more than a few on-siteWere here to help adaptations, the team has gone .lengths to ensure its crews safety while keeping the project on course.You need the right equipment, at the right place, right now. With an unmatchedAnd it wouldnt be doable, says rental fleet and branch network, we are ready to help you maximize productivityand protability. And our round the clock service and support means Morton, without all hands on the equipment will work just as hard as you do.deck: Weve been thrilled with the 160 Mountainview Rd relationship with our local Winnipeg Winnipeg, MB R3C 2E6 UnitedRentals.com team. Its (a) harmonious, capable and 204-775-7171 800.UR.RENTS well-functioning group, and its thanks2015 United Rentals, Inc. to them that were in a reallygood position.Watch The Arcs construction progress online at thearcwinnipeg.ca.38 BUILD MANITOBAwinnipegconstruction.ca'