THE ONLY SOURCE FOR PROFESSIONAL ICI ROOFING CONTRACTORS IN ONTARIO ORN
20 
ONTARIO ROOFING NEWS – ISSUE 3 2026
Option No.
Description
1
Like-for-Like Single-Ply TPO Roof Membrane System
2
Two-ply Modified Bitumen SBS Roof Membrane System
3
PMMA Liquid-Applied Roof Membrane System Applied over One-ply
Modified Bitumen SBS Base Sheet
Table 2: Roof membrane design option.
Blue Roofs
conductive medium. ASTM Guide 
D7877 and ASTM Practice D8231 
guided 
the 
electronic-detection-
conductive medium selection and 
design.26,27 The conductive medium 
sits between the polyisocyanurate 
insulation and the asphaltic cover 
board, comprised of welded stainless 
steel mesh. In consultation with the 
roofing membrane manufacturer, 
the conductive medium was placed 
below the cover board instead of 
directly below the membrane sys-
tem to protect the liquid-applied 
membrane. The mesh grid, spaced 
out at 50 mm by 50 mm (two in. 
by two in.), is connected through a 
contact plate and cable to a connec-
tion box. During ELD testing, a low-
voltage charge is applied through 
the connection box via a portable 
pulse generator.
Roof Drainage and Scuppers
The new replacement roof as-
sembly included the following 
drainage scope to accommodate the 
blue roof mechanical system design. 
Figure 10 and Figure 11 illustrate 
the blue roof drains connecting to 
the mechanical systems below the 
roof deck.
•  Upgrade the primary roof 
field drains, including add-
ing a field drain within the 
blue roof zone, to tie in the 
new roof assembly to the new 
blue roof mechanical sen-
sors, valves and water treat-
ment/storage systems below 
the deck.
•  Add new field overflow drains 
equipped 
with 
extension 
pipes rising above the roof 
membrane up to the maxi-
mum planned blue roof wa-
ter depth.
•  Add new overflow scuppers 
through the parapets set at 
the height of the maximum 
planned blue roof water 
depth.
The primary roof field drains 
control flow and pond water, and 
when the blue roof is inactive 
(e.g., in the winter months), they 
provide primary drainage to meet 
building design. These drains were 
retrofitted to include vandal-proof 
cast aluminum domes and hinged 
access gates, pan-formed aluminum 
drain bodies and cast aluminum 
clamping rings. The retrofit drains 
connected to the rainwater lead-
ers below the deck via mechanical 
coupling connections instead of 
U-flow friction insert seals, as the 
pipes may experience high flow rate 
and temporary backup conditions 
during blue roof drain down.
The overflow field drains and 
scuppers divert water and meet 
the roof’s drainage requirements, 
if the levels on the blue roof reach 
maximum planned storage capac-
ity. The overflow scuppers cut into 
the parapets’ drain through down-
spouts terminating at grade, as il-
lustrated in Figure 12. They were 
placed along the roof edge to make 
scuppers easier to inspect and were 
designed to complement the archi-
tectural style of the building, inte-
grating with the overall design.
Construction
Construction commenced with 
removal of the existing roof as-
sembly, followed by adjustments 
to existing roof anchors to extend 
them above the maximum planned 
water level. Surface preparation in-
cluded cleaning and priming of the 
existing concrete surface for vapour 
barrier application, while insulation 
was installed staggered and tightly 
butted. ELD conductive medium 
mesh was installed followed by 
cover board and one-ply modified-
bitumen SBS base sheet. Surface 
cleaning was carried out to remove 
any loose granules, dust or dirt 
prior to the liquid-applied PMMA 
system application. PMMA sys-
tem application is sensitive to high 
temperatures, which could lead 
to improper curing. Ambient and 
substrate temperatures were closely 
monitored throughout the process 
to verify application  onditions.
Uncovered concealed conditions 
during 
construction, 
including 
original structural roof deck pre-
cast panels construction tolerances, 
required some modifications to 
overflow drain and scupper levels to 
meet planned blue roof design wa-
ter storage capacity loads. Multiple 
methods to validate final installed 
new roof membrane levels were 
employed. Based on these actual site 
conditions, final blue roof water 
storage volume and overflow drain-
age heights were confirmed. Hand 
tape measurements, laser levels 
and total station surveys were com-
pleted during several stages during 
new roof assembly construction 
to confirm that the planned maxi-
mum storage capacity water levels 
were maintained.
After construction was com-
pleted and installation was commis-
sioned, blue roof water flood testing 
was conducted to validate the roof 
and flow control systems integrity. 
Mobile truck pumped 16,000 L 
(4,200 gal.) of water onto the roof, 
and a systematic monitoring pro-
gram was implemented to confirm 
the absence of leaks and proper op-
erations of the mechanical systems.
Discussion
Implementing this blue roof 
pilot project at the CVC Head Of-
fice in Mississauga is testing this 
emerging and innovative approach 
to urban water management and 
climate resilience. It provides valu-
able insights into the feasibility and 
practicality of blue roof installations 
in municipal settings, highlighting 
benefits and challenges encountered 
during the design and construc-
tion phases.
The pilot project incorporated 
an ongoing maintenance and moni-
toring program. The mechanical 
system includes drain sensors and 
control instruments to regulate 
flow. These components are sched-
uled for regular maintenance and 
monitoring to ensure proper per-
formance. The roof assembly’s em-
bedded EFVM conductive medium 
allows for regular testing for mois-
ture ingress and diagnostics in case 
of leaks.
Blue roofs, by design, increase the 
risk by intentionally ponding water. 
Structural load analysis, and incor-
porating redundancy and fail-safe 
mechanisms to the design, manages 
the risks. The design includes two 
separate types of overflow drainage 
pathways (i.e., scuppers and drain-
pipes) to prevent water accumula-
tion beyond safe levels. The roof 
membrane system and the drain sen-
sors include intentional redundancy 
to manage risks over the lifecycle 
Commercial and Residential Roofing
Trinity Roofing Ltd. specializes in a variety of roofing applications and  
waterproofing for residential, commercial and institutional buildings.
Phone: 416-630-9213 
Fax: 416-630-1722
URL: www.trinitycanada.com 
Email: info@trinitycanada.com 
Call For A Quote
651-398-3029
emiroofvacs.com
LEADERS IN ROOF 
VACUUM SALES

View this content as a flipbook by clicking here.