Figure 7: Superimposed dead load SDL cross-section diagram.
Figure 8: Roof plan.
technology, imposes a variable load 
due to rain. Importantly, OBC Ar-
ticle 4.1.6.4.(3) specifies that snow 
and rain loads do not coincide and 
should not be combined in the same 
load calculation.21 Consequently, 
the capacity of an existing roof to 
support a rainwater storage capacity 
is equal to the design snow or rain 
load. Based on the 2012 OBC and 
regional precipitation data, hydrau-
lic rain load calculations indicate 
that snow load typically governs de-
sign in Mississauga and Toronto, as 
shown in Table 1.
It is common practice that an 
increase of up to five per cent in 
variable load is acceptable without 
requiring structural reinforcement, 
translating to increasing ponding 
from 130 mm (five in.) to 137 mm 
(5.4 in.) in Mississauga. However, 
CVC’s requirement to store up to 
the maximum allowable amount of 
water necessitated a detailed assess-
ment and potential roof structural 
reinforcement. Design loads for the 
Roof A-1 were calculated, factoring 
a basic snow load of 1.3 kPa, wind 
uplift of 1.3 kPa and a basic super-
imposed dead load (SDL) of 1.6 
kPa. Additionally, the average slop-
ing topping dead load was 4.7 kPa, 
varying from 2.8 kPa to 6.6 kPa, as 
shown in Figure 7.
Accordingly, it was determined 
that the existing low-sloped roof 
can support basic seasonal blue roof 
technology without additional rein-
forcement, with a maximum snow 
load of 1.3 kPa plus 0.6 kPa in al-
lowances or a maximum ponding 
depth of 180 mm (seven in.). The 
blue roof system drains should re-
main open to avoid ponding during 
the winter months.
Roof Assembly
Considering Roof A-1’s existing 
TPO roof assembly condition and 
performance risks, full roof replace-
ment as part of the blue roof pilot 
was contemplated. Roof cut tests 
completed by CVC’s roofing con-
tractor confirmed moisture present 
below the existing TPO membrane 
at several locations. Concerns were 
raised regarding risks and the im-
pact of future leaks below the new 
blue roof, including building op-
erations disruption and hollow core 
structural roof slab deterioration. 
CVC elected to replace the full roof 
assembly as part of the blue roof 
project. Considerations and factors 
reviewed in making final new roof 
system design decisions are present-
ed below.
Blue Roofs
Design
Overview
To implement the blue roof proj-
ect on Roof A-1, a separation was 
needed to isolate existing rooftop 
building mechanical and weather-
monitoring instrumentation sys-
tems installed on the west section of 
the roof. Roof A-1 was divided by a 
new segregation barrier into two dis-
tinct areas: Zone 1 (the western third 
of the roof, which is to remain a con-
ventionally drained low-sloped roof) 
and Zone 2 (the eastern remaining 
roof area designated for blue roof 
water retention), as depicted in Fig-
ure 8. Zone 3, the lower garage roof 
(Roof A-2), falls outside this proj-
ect’s scope.
Roof Assembly
The new replacement roof assem-
bly at Zone 2 (the blue roof area), as 
a retrofit, was to at least achieve the 
same thermal and condensation re-
sistance performance levels of the ex-
isting TPO roof. Additional design 
decisions were guided by four key 
objectives established by the CVC. 
First was ensuring the new roof as-
sembly could allow for and perform 
under planned maximum water stor-
age volumes, above the membrane, 
for prolonged periods outside of 
winter conditions. The second ob-
jective was maintaining the high-
reflectivity white roof membrane 
surfacing design feature to reduce 
solar heat gain and building cooling 
energy loads. The third objective 
required that the roof membrane 
not impact the stored water’s qual-
ity and resist potential chlorine 
and algaecide water treatment ad-
ditives. Finally, the roof membrane 
needed to withstand light foot traf-
fic for demonstration and mainte-
nance purposes.
For the new roof membrane, the 
design team considered fully ad-
hered membranes with redundant, 
multi-ply and seamless applications 
to improve leak resistance and roof 
durability. A summary of the op-
tions reviewed is provided in Table 
2. All options included the same in-
sulation and vapour barrier details.
Given the following consider-
ations, the Option 3 roof assembly, 
including a PMMA liquid-applied 
membrane system over a one-ply 
modified-bitumen SBS base sheet, 
was ultimately selected.
•  The PMMA liquid-applied 
membrane is installed in a 
seamless application and can 
withstand the ponded water 
hydrostatic pressure antici-
pated in the RID blue roof 
City
Snow 
(without considering snow drift)
Water
Loading
kPa (psf)
Precipitation
mm (in.)
Loading
kPa (psf)
Precipitation
mm (in.)
Mississauga
1.28 (27)
130 (5.1)
1.11 (23)
113 (4.4)
Toronto
1.12 (23)
114 (4.5)
0.95 (19)
97 (3.8)
Table 1: Snow and rain loads as per Table 4.1.2.1A in 2012 OBC.21