Building A was designed in 2008 
by Montgomery Sisam Archi-
tects Inc. Accordingly, the 2006 
Ontario Building Code was the 
applicable building code at the 
time of design and permit issu-
ance. Design loading was in ac-
cordance with Part 4 of Division 
B. Environmental loading data 
for Mississauga was per Supple-
mentary Standard SB-1.
Feasibility Study
Project Background
In October 2017, the CVC 
authority began exploring the 
feasibility of implementing an 
RID blue-roof pilot project in-
stallation at their office building. 
This pilot project was seen as an 
opportunity to test the effective-
ness of this emerging technology 
in managing storm peak load, re-
ducing energy consumption and 
determining the non-potable 
demand that could be met by 
the existing rainwater harvesting 
(RWH) system.10 Over the fol-
lowing months, CVC engaged 
with internal and external stake-
holders to refine the project con-
cept and secure funding. Due 
to its size and relatively minimal 
mechanical and conduit conges-
tion, Roof A-1 was identified as 
a candidate for the installation of 
the blue roof system.
In light of the prevailing code 
regulations in 2017, which al-
lowed a maximum rainwater 
drain-down time of 24 hours per 
day and a maximum roof rain-
water level of 150 mm (six in.), 
CVC entered pre-consultation 
and technical discussions with 
the City of Mississauga Building 
Department to determine the 
legislative requirements for a blue 
roof. In addition to complying 
with the general requirements of 
the OBC, two alternative solu-
tions were proposed under OBC 
Division C to maximize the ben-
efits of a blue roof.
The first alternative, Solu-
tion A, proposed extending the 
maximum allowable rainwater 
drain-down time to six days. 
This extension aimed to increase 
the amount of water stored while 
also including provisions for re-
ducing the likelihood of mould 
or mildew growth and the risk 
of illness from unsanitary con-
ditions caused by contaminat-
ed surfaces and vermin.29 This 
latter concern was particularly 
pertinent in relation to Culex 
mosquitoes, whose larval de-
velopment cycle can be as early 
as five days with favourable en-
vironmental conditions.30 Cu-
lex mosquitoes in this region 
are known to carry the West 
Nile virus, and stagnant water 
without treatment may lead to 
increased larval development, 
potentially spreading the dis-
ease.31 According to this alter-
native solution, all accumu-
lated rainwater must be treated 
every two days per CSA B805 
standards to control bacteria 
and protozoa.28,29
The 
second 
alternative, 
Solution B, suggested increas-
ing the maximum allowable 
roof rainwater level from 150 
mm (six in.) to 250 mm (10 
in.). The City of Mississauga 
requested a detailed structural 
assessment and the inclusion 
of additional overflow scup-
pers to manage this increased 
capacity and alleviate the risk 
of structural overloading on 
the existing structure.
Structural
The 
original 
structural 
deck was designed to accom-
modate dead, live, variable and 
wind loads, according to OBC 
2012, Table 4.1.2.1.A. Dead 
loads include the self-weight 
of the structure, permanent 
construction materials, roof 
assembly, overburden, rooftop 
equipment and architectural 
components. Live and variable 
loads account for occupants, 
movable equipment and en-
vironmental factors such as 
snow, ice and rain. For most 
roof structures, the variable 
snow or rain load is equal to 
or greater than the dead load, 
with the dead load calculated at 
1.25 kPa (26 psf) and the vari-
able load at 1.5 kPa (31 psf), 
per OBC Table 4.1.3.2.A.21
The rainwater storage ca-
pacity, integral to blue roof 
While prototypes exist for tray systems, check-dammed systems and blue-green roofs, 
limited research and case studies exist for RID systems, flagging a potential area for 
further research and development.