The Canadian Construction Documents 
Committee (CCDC) has released two 
new contract templates that will be of 
interest to owners, design-builders and 
contractors across Canada. The CCDC 
14 – 2026 Design-Build Stipulated Price 
Contract and the CCDC 32 – 2026 
Progressive Design-Build Contract each 
bring notable updates and innovations 
to the design-build delivery model. This 
article provides an overview of the key 
features of these new standard  
form contracts.
CCDC 32 – 2026 PROGRESSIVE 
DESIGN-BUILD CONTRACT
The CCDC 32 – 2026 Progressive 
Design-Build Contract represents 
an innovative hybrid approach, 
combining elements of the construction 
management and design-build contract 
models into a delivery framework 
that contemplates both significant 
pre-construction work and final 
construction phases.
Conceptually, CCDC 32 contemplates 
a “project development phase” that 
produces a “final project proposal.” 
The acceptance of that final project 
proposal by the owner triggers the 
commencement of the “design/
construction phase.” The contract also 
provides for the possibility of issuing 
“early work authorization” to complete 
work that would otherwise be deferred 
until the commencement of the design/
construction phase. In anticipation of an 
extended duration for the project, the 
contract includes provisions that provide 
clarity and direction on the timing and 
manner in which fee arrangements are 
to be reviewed.
One of the most notable innovations in 
CCDC 32 is the introduction of “project 
gates.” These are formal decision points 
during the project development phase 
that require owner acceptance for the 
project to advance to the next project 
gate and, ultimately, to the submission 
and acceptance of the final project 
proposal. Six such project gates are 
contemplated, with distinct submission 
requirements set out by default, though 
these may be modified by the parties  
as necessary. The introduction of  
project gates should help keep project 
costs and risks within the tolerance  
of the parties throughout the 
development process.
CCDC 32 requires the design-builder 
to enter into a contract with the 
consultant based on the current version 
of the CCDC 33 – 2026 Progressive 
Design-Build Service Contract Between 
Design-Builder and Consultant, which 
incorporates the terms and conditions 
of the progressive design-build contract. 
Any modification or extension of the 
consultant’s duties, responsibilities 
or limitations of authority requires the 
written consent of the owner. Notably, 
the CCDC 33 standard form contract 
includes, by default, both the owner’s 
statement of requirements and the final 
project proposal, which form part of the 
CCDC 32 contract between owner  
and design-builder.
CCDC 32 also includes ready-for-
takeover and early occupancy provisions 
and incorporates schedules which, if 
properly completed, provide valuable 
guidance on who is responsible for 
the various services contemplated 
by the contract and how payment for 
those services is to be determined. The 
contract also includes some notable 
general improvements to basic contract 
terms, such as a requirement for the 
release of holdback not later than 10 
working days after the expiration of the 
applicable holdback/lien registration 
period and improvements to the 
language respecting what can be 
recovered for work performed pursuant 
to a change directive.
Manitoba readers should note that the 
usefulness of the CCDC 32 contract 
in this province will be limited by the 
Builders’ Liens Act, which does not 
permit progressive release of holdback 
on the same basis as contemplated by 
the contract. While the Act does allow 
for interim release of holdback, it does 
so only on a subcontract-by-subcontract 
basis, rather than on a project-wide 
progressive basis. Nevertheless, 
CCDC 32 may still prove to be a 
useful delivery model for owners and 
contractors in Manitoba, particularly 
given its structured approach to project 
development through the project  
gates framework.
CCDC 14 – 2026 DESIGN-BUILD 
STIPULATED PRICE CONTRACT
The CCDC 14 – 2026 Design-Build 
Stipulated Price Contract introduces 
several notable updates to the more 
familiar CCDC 14 – 2013. Among the key 
changes are payment terms, which are 
now compatible with prompt payment 
legislation, reflecting the legislative 
developments that have occurred 
across Canadian jurisdictions since the 
previous edition. This update ensures 
that the standard form contract can be 
used without significant modification 
in provinces that have implemented 
prompt payment regimes.
The 2026 edition also introduces an 
express mutual waiver of consequential 
damages – a provision that will provide 
greater certainty to both parties 
regarding the scope of their potential 
liability. Additionally, the contract now 
includes ready-for-takeover provisions 
similar to those found in other updated 
CCDC documents, providing clearer 
mechanisms for the transition of the 
project from the design-builder to  
the owner.
Insurance requirements have also been 
updated, with increases in the amounts 
By Daryl A. Chicoine
NEW CCDC  
CONTRACT TEMPLATES:
A first look at CCDC 14 – 2026 and CCDC 32 – 2026