20 BUILD MANITOBA winnipegconstruction.ca BENCHMARKS The Canadian Construction Documents Committee (CCDC) has released two new contract templates that will be of interest to owners, design-builders and contractors across Canada. The CCDC 14 – 2026 Design-Build Stipulated Price Contract and the CCDC 32 – 2026 Progressive Design-Build Contract each bring notable updates and innovations to the design-build delivery model. This article provides an overview of the key features of these new standard form contracts. CCDC 32 – 2026 PROGRESSIVE DESIGN-BUILD CONTRACT The CCDC 32 – 2026 Progressive Design-Build Contract represents an innovative hybrid approach, combining elements of the construction management and design-build contract models into a delivery framework that contemplates both significant pre-construction work and final construction phases. Conceptually, CCDC 32 contemplates a “project development phase” that produces a “final project proposal.” The acceptance of that final project proposal by the owner triggers the commencement of the “design/ construction phase.” The contract also provides for the possibility of issuing “early work authorization” to complete work that would otherwise be deferred until the commencement of the design/ construction phase. In anticipation of an extended duration for the project, the contract includes provisions that provide clarity and direction on the timing and manner in which fee arrangements are to be reviewed. One of the most notable innovations in CCDC 32 is the introduction of “project gates.” These are formal decision points during the project development phase that require owner acceptance for the project to advance to the next project gate and, ultimately, to the submission and acceptance of the final project proposal. Six such project gates are contemplated, with distinct submission requirements set out by default, though these may be modified by the parties as necessary. The introduction of project gates should help keep project costs and risks within the tolerance of the parties throughout the development process. CCDC 32 requires the design-builder to enter into a contract with the consultant based on the current version of the CCDC 33 – 2026 Progressive Design-Build Service Contract Between Design-Builder and Consultant, which incorporates the terms and conditions of the progressive design-build contract. Any modification or extension of the consultant’s duties, responsibilities or limitations of authority requires the written consent of the owner. Notably, the CCDC 33 standard form contract includes, by default, both the owner’s statement of requirements and the final project proposal, which form part of the CCDC 32 contract between owner and design-builder. CCDC 32 also includes ready-for- takeover and early occupancy provisions and incorporates schedules which, if properly completed, provide valuable guidance on who is responsible for the various services contemplated by the contract and how payment for those services is to be determined. The contract also includes some notable general improvements to basic contract terms, such as a requirement for the release of holdback not later than 10 working days after the expiration of the applicable holdback/lien registration period and improvements to the language respecting what can be recovered for work performed pursuant to a change directive. Manitoba readers should note that the usefulness of the CCDC 32 contract in this province will be limited by the Builders’ Liens Act, which does not permit progressive release of holdback on the same basis as contemplated by the contract. While the Act does allow for interim release of holdback, it does so only on a subcontract-by-subcontract basis, rather than on a project-wide progressive basis. Nevertheless, CCDC 32 may still prove to be a useful delivery model for owners and contractors in Manitoba, particularly given its structured approach to project development through the project gates framework. CCDC 14 – 2026 DESIGN-BUILD STIPULATED PRICE CONTRACT The CCDC 14 – 2026 Design-Build Stipulated Price Contract introduces several notable updates to the more familiar CCDC 14 – 2013. Among the key changes are payment terms, which are now compatible with prompt payment legislation, reflecting the legislative developments that have occurred across Canadian jurisdictions since the previous edition. This update ensures that the standard form contract can be used without significant modification in provinces that have implemented prompt payment regimes. The 2026 edition also introduces an express mutual waiver of consequential damages – a provision that will provide greater certainty to both parties regarding the scope of their potential liability. Additionally, the contract now includes ready-for-takeover provisions similar to those found in other updated CCDC documents, providing clearer mechanisms for the transition of the project from the design-builder to the owner. Insurance requirements have also been updated, with increases in the amounts By Daryl A. Chicoine NEW CCDC CONTRACT TEMPLATES: A first look at CCDC 14 – 2026 and CCDC 32 – 2026
View this content as a flipbook by clicking here.