b'The Final RehabBRIGHTON PITTown of BrightonCBM Aggregates - A Division of Votorantim CimentosIn October 2019, Brighton Pit completed work on its seven-hectare rehabilitation project. The initiative started in April 2017 with Behan Construction grading and shaping the existing overburden in the distributed area to create to a 3:1 slope that supports surface water drainage towards the sites pond. Existing overburden was then applied and graded over the floor of the former plant area and haul road, and approximately 2,500 cubic metres of topsoil taken from on-site storage berms was distributed over the area at a minimum thickness of six inches. After the topsoil was applied, crews applied 875 kilograms of seed at a rate of 125 kg per hectare.OSSGAs Progressive Rehabilitation Award recognizes ongoing efforts of individual operators in progressively rehabilitating their sites in accordance with their site plans. Overall, the OSSGA Industry Recognition Awards program recognizes a wide range of activities that contribute to a progressive image of our member aggregate producers and the aggregate industry as a whole. A key goal is to raise the bar by highlighting operations that go above and beyond what is required by legislation.For more information on OSSGAs Industry Recognition Awards, visit ossga.com38 AVENUESWINTER 2022'